The problem: Electric Glass Fibre UK had invested in two new gas-powered furnaces.
Fifty meters of 4”- 2” mild steel pipework was required to supply the new furnaces with natural gas.
Our solution:
Our commercial gas engineers were called in to install the new gas pipework.
Both welded and screwed methods were used in order to fit the new pipework.
Once the installation was complete a commercial gas tightness test and direct purge were undertaken.
After a successful test and purge, a Gas Safe certificate was issued, ensuring the new industrial gas pipework was ready to use.
Tasks involved:
Steel pipework fabrication
Screwed pipework installation
Gas purging
Gas tightness test
Gas pipework commissioning
Gas Safe certificate